[redacted] Nature of Complaint: Response #000000;">Please see attached the quote for the work agreed upon by 3B and [redacted] is correct the was supposed to start on 4/*/14, however due to the unorthodox shape of [redacted] base cabinet the cabinet manufacturer requested additional field measurements which delayed their deliveryWe called in the tub re-glazing contractor so we could at least get some of the work completedAs far as the sink and counters are concerned, the counters were scheduled to be installed on a weekend only to find out from [redacted] no work could be performed in the building on the weekendsIt took approximately one week to get [redacted] ***’ installation back on the installer’s scheduleWe tried diligently on numerous occasions to work with [redacted] ***’ material choices but found that most of her choices had a very long lead timeIn an offer of good faith I drove [redacted] in my personal vehicle to Home Depot in the Bronx, Home Depot and Lowes in [redacted] so she could personal select material which was in stock and more readily availableThe cabinet door had a defective hinge and it was replaced [redacted] was unsure as to where she wanted the shelving space so we left them out until she decided and when she did we installed themWe will happily install the shelves in [redacted] mirrored medicine cabinetI agree that the project took longer than expected and apologizes for any inconvenience this may have caused Desired Outcome 3B General request an opportunity to cure any open issues Compensation for the delay is open for discussion Final Payment Please call me to discuss prior to forwarding response [redacted] [redacted] [redacted] [redacted] [redacted] [redacted]

Revdex.com:
I have reviewed the response made by the business in reference to complaint ID [redacted], and find that this resolution is satisfactory to me and the matter has been resolved.
Sincerely,
[redacted]

[redacted]
 
Nature of Complaint: Response
 
#000000;">Please see attached the quote for the work agreed upon by 3B and [redacted] is correct the was supposed to start on 4/*/14, however due to the unorthodox shape of [redacted] base cabinet the cabinet manufacturer requested additional field  measurements which delayed their delivery. We called in the tub re-glazing contractor so we could at least get some of the work completed. As far as the sink and counters are concerned, the counters were scheduled to be installed on a weekend only to find out from [redacted] no work could be performed in the building on the weekends. It took approximately one week to get [redacted]’ installation back on the installer’s schedule. We tried diligently on numerous occasions to work with [redacted]’ material choices but found that most of her choices had a very long lead time. In an offer of good faith I drove [redacted] in my personal vehicle to Home Depot in the Bronx, Home Depot and Lowes in [redacted] so she could personal select material which was in stock and more readily available. The cabinet door had a defective hinge and it was replaced. [redacted] was unsure as to where she wanted the shelving space so we left them out until she decided and when she did we installed them. We will happily install the shelves in [redacted] mirrored medicine cabinet. I agree that the project took longer than expected and apologizes for any inconvenience this may have caused.
 
Desired Outcome
 
1.       3B General request an opportunity to cure any open issues.
2.       Compensation for the delay is open for discussion.
3.       Final Payment
 
Please call me to discuss prior to forwarding response.
[redacted]
 
[redacted]
 
 
[redacted]
 
[redacted] [redacted] [redacted] [redacted] [redacted] [redacted] [redacted] [redacted] [redacted] [redacted] [redacted] [redacted] [redacted] [redacted] [redacted] [redacted] [redacted] [redacted] [redacted] [redacted]
 
 
 
[redacted]
 
[redacted]

Review: In February of 2014, I hired a contractor to replace my kitchen cabinets and counter tops, and to Re-glaze my bathtub, I received a proposal via e-mail, and I agreed with the price that was quoted because it fell within the money that I had in my budget for the work to be done. The original price quoted to me for the work to be done on my kitchen and bathroom was $3,387.81. A contract was then drawn up by [redacted], and was signed by the both of us. The work was to have started on April *, 2014. I gave [redacted] a cashier's check for $2,000. on March **, 2014, after I had paid the deposit I decided to replace my bathroom basin and vanity and medicine cabinet, so I gave [redacted] (who is also a partner in the company) a cash payment of $782.00 and I was given a receipt on April **, 2014. The work was to have started on April *, 2014 on April **, 2014 the only work that had been done was the Re-glazing of my bath tub. My old cabinets were not removed until May *, 2014, my new cabinets sat on my kitchen and living room floors until May **, 2014 when they were installed. My sink and counter tops were not installed until June **, 2014., the bathroom vanity and medicine cabinet were just installed on June **, 2014. Now after all this delay in having the job completed, [redacted] wants to ask for a final payment, the only problem with that request is the job has not been completed, (1) One of the doors on my cabinets is falling off, (2) the shelves in another one of the cabinets have not been put in place, (3) the shelves in the medicine cabinet have not been put in place. I've been terribly inconvenienced by the delay of this job, and I think I should be compensated by the company in some manner.Desired Settlement: When the job is completed to my satisfaction, we can consider the matter settled.

Business

Response:

[redacted]

Nature of Review: Response

Please see attached the quote for the work agreed upon by 3B and [redacted] is correct the was supposed to start on 4/*/14, however due to the unorthodox shape of [redacted] base cabinet the cabinet manufacturer requested additional field measurements which delayed their delivery. We called in the tub re-glazing contractor so we could at least get some of the work completed. As far as the sink and counters are concerned, the counters were scheduled to be installed on a weekend only to find out from [redacted] no work could be performed in the building on the weekends. It took approximately one week to get [redacted]’ installation back on the installer’s schedule. We tried diligently on numerous occasions to work with [redacted]’ material choices but found that most of her choices had a very long lead time. In an offer of good faith I drove [redacted] in my personal vehicle to Home Depot in the Bronx, Home Depot and Lowes in [redacted] so she could personal select material which was in stock and more readily available. The cabinet door had a defective hinge and it was replaced. [redacted] was unsure as to where she wanted the shelving space so we left them out until she decided and when she did we installed them. We will happily install the shelves in [redacted] mirrored medicine cabinet. I agree that the project took longer than expected and apologizes for any inconvenience this may have caused.

Desired Outcome

1. 3B General request an opportunity to cure any open issues.

2. Compensation for the delay is open for discussion.

3. Final Payment

Please call me to discuss prior to forwarding response.

Consumer

Response:

I have reviewed the response made by the business in reference to complaint ID [redacted], and find that this resolution is satisfactory to me and the matter has been resolved.

Sincerely,

Check fields!

Write a review of 3B General Construction LLC

Satisfaction rating
 
 
 
 
 
Upload here Increase visibility and credibility of your review by
adding a photo
Submit your review

3B General Construction Rating

Overall satisfaction rating

Description: CONSTRUCTION & REMODELING SERVICES

Address: 478A Decatur St, Brooklyn, New York, United States, 11233

Phone:

Show more...

Add contact information for 3B General Construction

Add new contacts
A | B | C | D | E | F | G | H | I | J | K | L | M | N | O | P | Q | R | S | T | U | V | W | X | Y | Z | New | Updated