Sign in

RCW Design

210 S 1st St, Shepherd, Michigan, United States, 48883

Sharing is caring! Have something to share about RCW Design? Use RevDex to write a review
Reviews Cabinet Maker, Woodworking RCW Design

RCW Design Reviews (%countItem)

We initiated a project with Reynolds Custom Woodworking in good faith. During the course of the project we learned of the following violations with Reynolds Custom Woodworking and their representatives:

Bruce R and Reynolds Custom Woodworking indicated they were in possession of a contractors license; we were unable to find evidence of such a license

We requested Reynolds Custom Woodworking obtain permits on the renovations in our home and they did not get the required permits needed to conduct almost 80K of renovations to our existing structure.

They were unable or unwilling to account for funds coming in their possession through our bank loan and direct payment. They did not pay bills for materials and without our knowledge did not reconcile a bill with *** and a lien was activated against our home.

They failed to get a signed agreement and did not document cost changes after repeated violations and cost additions.

They replaced the qualified sub-contractors in the estimate with unlicensed contractors working on electrical, mechanical, and plumbing in our home.

They used a builders license without his permission on the loan documents for the contractor work on the renovation loan.

They collected funds for required permits that were not procured.

They were unwilling or unable to deliver the services on our project in a timely manner and within the timeframe defined by the bank renovation loan and loan officer.

They showed gross negligence and incompetence when undertaking aspects of the job they were unqualified to complete including: Not protecting the house while under construction leading to a flood and subsequent mold infestation; four rebuilds of the fireplace frame each time necessitating a rebuild due to violation of installation instructions and safety requirements; inability to implement computer aided design resulting in inaccurate measurements, dimensions, and details that impacted the communication of project design to sub-contractors and home owners.
Product_Or_Service: Contractor and cabinetry for home renovations

Desired Outcome

Other (requires explanation) Account for funds procured on behalf of the project; provide itemized receipts and sub-contractor bills showing payment for services; reconcile accounts with sub-contractors to remove liens and provide waivers; pay restitution for poor workmanship

RCW Design Response • Dec 23, 2019

Toni,
Below is a response to each item on complaint, case #***

Indicated we were in possession of a builder license: We, under no circumstances implied or stated that we were in possession of a builder license. We had numerous conversations about us only being an entity that coordinated the subcontractors to complete the project.

Obtaining Permits: We did indicate that we would be using permits to do renovations on the home

Unable or unwilling to account for funds: We, in no way, were unwilling to account for funds coming into our possession. There was an instance at our last meeting where an amount was in question of which I responded that I would investigate it because at that given moment I could not find where it came from. When working on the sworn statement the title company had me move a few things around in order to keep things balanced and get the fund to the correct contractors.

Did not pay bills resulting in lien: The bill in question was an additional cost, chosen as an adder, to the project that the client refused to pay.

Did not document cost changes and additions: All documented cost changes were made on an invoice that was viewable at any time via a link (that the client had access to) to a QuickBooks online invoice. Each of the changes were acknowledged by the client as additional costs. There were no signed agreements between Reynolds Custom Woodworking and the client when these changes were made. Many of these costs were offset by Reynold Custom Woodworking forfeiting funds to try and ease the tension between the client and Reynold Custom Woodworking.

Replaced qualified sub-contractors: The sub-contractors used for the mechanical, plumbing and electrical were and are still licensed in their fields. Reynolds Custom Woodworking did wire a small portion of the renovation on the existing structure without a permit and does no have a license to do so. The builder moved an existing exterior water line temporarily in order to continue working on constructing the deck. The licensed plumber had already been scheduled to go in to finish the work. I am unsure what mechanical is being referred to.

Used a builder's license without permission: We did not use a builder license without the permission of the contractor. We received a formal quote for the structure of the addition from a builder at which point he sent us his builder license information to be sent to the financial institution. As the project progressed, we began getting the forms around for the permits required for the project. After we had all the paperwork ready to file, we contacted the builder to have him sign off on the forms at which point he informed us that he would not be doing this project. At this point we began to search for, and found, another licensed builder to complete the work. This process was discussed with the client at the time of the events.

Collected funds for permits: Reynolds Custom Woodworking never received any funds for permits.

Unwilling or unable to deliver in timely manner: There are many aspects that held this project from being completed in the time allotted by the financial institution. The foundation for the addition was held up due to weather. Issue with timelines for subcontractors were are result of the late start on the new structure. In addition, we received 3 separate punch lists. Each one was close to completion when a new one was issued. Reynolds tried to appease the client and complete these items as quickly as possible. Some of the issues that the client has/had were well within tolerance of building norms but deemed unacceptable by the client. We were on track to complete the project by the necessary completion date (12/13/19) when we were removed as a contractor from the project and asked to vacate the home.

Not protecting the home: The foundation was set, and we were waiting for inspector to inspect the foundation so we could backfill the new structure. We received a half inch of rain one evening which resulted in the basement being wet. Not flooded. There floor was wet for approximately 14 ft along the foundation and out approximately 4 ft. A restoration company came in and pulled some of the drywall off to inspect the wet areas for mold, which they found and remediated it. The drywall was then replaced, and a paint allowance gave to the client for the damages. No of which the client as asked to pay for. At the time of the foundation completion Reynolds dug a trench pitched away from the home to drain water in the event there was rainfall before the backfill was completed. This was done before the water damage occurred.

Fireplace rebuild: The fireplace was built the first time as the client described in a meeting that took place for an aesthetically pleasing outcome. This was completed by the builder that put up the new structure. As we began to get further into the project, we found that some of the dimension were not within the manufacturers requirements to meet their safety codes. As a result, we had a meeting with the fireplace installer and to our understanding, built the fireplace to the specifications needed for a proper installation. There was a miscommunication as to where the fireplace was to be set which resulted in there needing to be an additional panel added to the face of the structure to meet code. All of this was completed as quickly as we could get an understanding from the fireplace manufacturer to ensure there was not any additional work that needed to be done.

Inability to implement computer aided design: I am unsure of what is being addressed here and unsure the relevance.

I urge you to please contact *** at *** Bank in *** if you have any financial related questions on this matter. Below is her contact information.

Customer Response • Dec 30, 2019

(The consumer indicated he/she DID NOT accept the response from the business.)
Below are our responses, numbered to match paragraphs in the responses provided by Reynolds Custom Woodworking (RCW):
1. The response from RCW is untruthful; RCW did not address their lack of licensure or legality of serving as an unlicensed contractor on any project exceeding $600.
2. RCW confirmed they stated they would obtain permits; RCW did not provided an explanation for why they did not acquire permits. In Dec 2019 ***, *** Twp. Building Inspector, confirmed the code violation for performing work on our home without a permit.
3. The response from RCW is untruthful; RCW has not shared project receipts or documentation for expenditures and/or funds collected despite repeated and ongoing requests. We had a straight materials and labor agreement with RCW; for their contractor services, we were to pay 5% on materials and 10% on subcontractor labor. This agreement was followed through 5/19 and multiple incidences of accounting errors, double billing, billing for services not rendered, unapproved additional costs, and quote inaccuracies were detected. After 5/19, RCW refused to provide receipts or documentation of expenditures despite repeated requests. Conservatively, we have questions on over $12,000 in undocumented expenses; RCW is unable or unwilling to provide receipts or documentation for these or any other funds collected (for examples of billing discrepancies see #4 for non-payment of bills; #5 for unapproved cost changes; #8 for collecting funds for services not rendered).
4. The response from RCW is untruthful. Without our knowledge and prior to being terminated on 12/4/19, RCW instructed *** Lumber (DL) to place a lien on our home to collect $2,333 for decking material billed to RCW and delivered to our home in 8/19. During an 8/29/19 meeting with RCW and *** (AE) from MB, the upgrade to composite decking material was specifically addressed. It was confirmed and documented by email that same day, that credits from the fireplace install would be used to offset the added cost of composite decking. At a 11/27/19 meeting with RCW and AE, RCW never indicated they had a bill in arrears with DL or that they were unable/unwilling to pay this bill. Since our initial complaint, we learned that prior to being terminated, RCW also contacted ***, instructing them to file a lien against our home for payment of bills RCW was unwilling/unable to pay.
5. The response from RCW is untruthful. Per our agreement with RCW and the Builders Construction Acknowledgment signed by Bruce R on 11/19/18 and submitted to MB, all cost changes needed to be preapproved, documented, and signed by both the builder and borrower. Despite these agreements, RCW repeatedly billed us for unapproved costs. We first encountered unapproved costs in 5/19. At a meeting to resolve this bill (paid 5/21/19), RCW agreed to use a Google Doc to communicate and confirm future cost changes. On 7/30/19, a new invoice was generated with undocumented and unapproved cost changes. After repeated requests to discuss the bill, we employed the assistance of AE at MB to bring RCW to the table to discuss billing discrepancies (among many issues). AE oversaw a meeting on 8/29/19 where we reiterated the need to document cost changes and RCW, again, agreed to use the Google Doc. On 11/15/19, RCW requested the final draw with no accounting updates nor a final invoice. The final invoice was first made available on 11/26/19, when we were again presented with undocumented and unapproved cost changes totaling almost $14,000. Despite multiple discussions, at no time did RCW get appropriate documentation for pre-approval of cost changes (via the Google Doc or any other method) nor maintain current and accurate invoices (in QuickBooks or any other format).
6. RCW confirmed they performed unlicensed and unpermitted electrical, mechanical, and plumbing work. RCW did not address transferring >$5000 designated for licensed and skilled subcontractors (***; ***( CHP); ***; and ***), to unqualified and unlicensed RCW employees. RCW did not address restitution for poor workmanship that did not meet industry standards (e.g., dimmer lights with incorrect wiring; tile with excessive lippage and jagged/flaked/chipped edges; and wood flooring gaps >1/4 inch). We provided RCW multiple opportunities to fix these issues and RCW declined to address the lights, made 3 failed attempts to improve tile installation, and made an unacceptable offer to revisit wood flooring issues in six months after we had paid in full for the project.
7. The response from RCW is untruthful. We spoke to *** (owner ***) and he indicated he never approved of nor was aware that RCW submitted his information to MB. MB was unaware *** was no longer the builder and his name is still affiliated with the loan. We talked with the *** Twp. Building Inspector, who informed us that RCW applied for a building permit (covering just the addition and deck) using invalid license numbers and then submitted the application using ***'s license. *** sent a registered letter to the Building Inspector requesting his name be removed from the permit and subsequently withdrew from the project. RCW did not inform us that they had obtained another builder (***) to replace *** until after *** started work on the addition (*** obtained a permit for the addition on 6/26/19). We only learned of this change after questioning Bruce R on 6/29/19.
8. The response from RCW is untruthful. RCW collected $800 in 1/19 and $400 in 4/19 specific to obtaining permits. On 6/19/19 Bruce R provided MB with a full unconditional waiver of lien for permits. As of 6/19/19 no permits had been obtained for any element of the renovation or construction on our home.
9. The response from RCW is untruthful. RCW was untimely during the entire project and consistently missed deadlines. They were not on track toward completion with major items remaining incomplete through 12/4/19 when we terminated them as our contractor. We mentioned these issues on multiple occasions, including: grouting for tile installed in 4/19; damaged/faulty cabinetry installed in 5/19 and paid in full for >6 months; electrical work for dimmable lights in kitchen dating back to 6/19; roof/gutter issue dating back to 7/19; surround, painting, and mantel for a fireplace installed in 8/19; and an incomplete corner on a deck installed in early 9/19. RCW requested a final draw on 11/15/19 with no plan for completing the remaining work, leaving us vulnerable to a fully paid but partially completed project. RCW pushed for incomplete/faulty work to be paid before it was completed, double billed us for items paid in full, and did not address punch list items in a time frame that allowed for completion prior to final loan disbursement.
10. The response from RCW is untruthful. Basement water damage and mold growth resulted from having no seal between the addition and home and non-functioning drainage of foundation trench. We engaged *** Remediation to address the mold growth, who contacted RCW on our behalf for payment as RCW was not responding to our calls and texts. In 10/19, we received a quote from RCW to fix the basement paint and trim, which was to be paid entirely by us with no allowance to cover flood damage. RCW had not addressed this issue as of 12/4/19 when we terminated them as our contractor.
11. The response from RCW is untruthful. The frame for the wood-burning fireplace required a rebuild on four occasions due to RCW's violations of code or manufacturer requirements. We engaged CHP (installer), *** (fireplace manufacturer), and the inspector on multiple occasions to reiterate to RCW the requirements for safe installation. RCW was informed of these issues prior to each rebuild of the framing yet continued to not meet specifications. We and CHP were pressured to continue in violation of installation recommendations, resulting in combative calls and discussions, extended work shutdowns, and additional fees for RCW labor to fix their mistakes. This issue first arose in early 7/19. The last of four required rebuilds arose in late 10/19 and resulted in a work stoppage for all of 11/19. During this time we experienced considerable pressure to accept substandard and unsafe work, as a final draw had been requested and the end of the loan period was imminent. As of 12/4/19 the fireplace was still not installed correctly.

On 12/19/19 we received a registered letter from RCW dated 12/16/19, which was sent after we submitted the Revdex.com complaint and had paid $9,700 to cover RCW's unpaid bills and avoid liens. RCW letter included a bill for undocumented additional costs and an offer to "cure" the poor workmanship. Neither the issues raised in the Revdex.com complaint nor desired resolutions were addressed in the letter or

RCW Design Response • Jan 13, 2020

1. RCW did express to the *** that we would be a general contractor on their project and did not have a license.
2. N/A
3. The *** were given the option prior the start of this project to either have bids for the entire project or time and material. They chose a bid type due to the uncertainty of a time and material in hopes to get a more accurate quote. At this time, we agreed upon a 10% General contracting fee which was to be added to each of the subcontractor's bids for the project
4. The lien from *** Lumber was in lieu of Reynolds being terminated from this project. As stated before, this was an additional item to their project. The lien from *** was in lieu of Reynolds being terminated from this project. All funds acquired for *** were paid to *** with an additional item that was not part of the original bid left as a balance.
5. Many, if not all of these additional costs were absorbed by Reynolds after the 11/26/19 invoice in an effort to ease tension between the two parties. Please see attachment for final overages.
6. Each of the fund's transfers were approved by the *** at the time of each draw. Reynolds did address many issues including all items listed. This may not have been to the liking of the *** but the items left were within what should be considered industry standards. For the items in question Reynolds offered viable solutions to try and appease both sides. The *** were never instructed or pressured to pay any items in full if they were not acceptable workmanship.
7. The *** were made aware of the building company change at the time we were having issues with acquiring a builder. We were in contact with *** before preparing permits for this project giving him an estimated start date and discussed possible delay issue due to weather.
8. These funds were reimbursed on the final billing. Please see attachment.
9. We maintain our original response. Unwilling or unable to deliver in timely manner: There are many aspects that held this project from being completed in the time allotted by the financial institution. The foundation for the addition was held up due to weather. Issue with timelines for subcontractors were a result of the late start on the new structure. In addition, we received 3 separate punch lists. Each one was close to completion when a new one was issued. Reynolds tried to appease the client and complete these items as quickly as possible. Some of the issues that the client has/had were well within tolerance of building norms but deemed unacceptable by the client. We were on track to complete the project by the necessary completion date (12/13/19) when we were removed as a contractor from the project and asked to vacate the home
10. The water damage was not a result of faulty planning or workmanship from Reynolds or any of its subcontractors. The foundation of the home was and had to be exposed to the elements. Reynolds sent someone over as soon as they were able. The quote from 10/19 was to replace all casing and base in the basement room which was requested by ***. It was expressed that they would like to renovate this room in its entirety, although this was not needed, because of the damage that was done. A credit was given on the final invoice, please see attachment. The issue was not addressed by Reynolds because the *** decided that they were going to do the work themselves if there was a credit given for damages.
11. We maintain our original response but also like to state that the fireplace mantle and surround meets or exceeds the manufacturers requirements. Fireplace rebuild: The fireplace was built the first time as the client described in a meeting that took place for an aesthetically pleasing outcome. This was completed by the builder that put up the new structure. As we began to get further into the project, we found that some of the dimension were not within the manufacturers requirements to meet their safety codes. As a result, we had a meeting with the fireplace installer and to our understanding, built the fireplace to the specifications needed for a proper installation. There was a miscommunication as to where the fireplace was to be set which resulted in there needing to be an additional panel added to the face of the structure to meet code. All of this was completed as quickly as we could get an understanding from the fireplace manufacturer to ensure there was not any additional work that needed to be done.

Customer Response • Jan 19, 2020

(The consumer indicated he/she DID NOT accept the response from the business.)
We terminated Reynolds Custom Woodworking (RCW), Bruce R, and Matt R due to their illegal, unethical, and unprofessional activity relative to the renovation of our home. We terminated RCW when we learned they had left us vulnerable to being legally and financially liable for: faulty, unpermitted, and unlicensed work; unpaid subcontractors with RCW accounts in arrears; pending liens against our home; an incomplete and poorly executed renovation; and unsafe work requiring a significant outlay of funds to meet code. Nothing in the response from RCW indicates a genuine attempt to work with us or to mitigate the financial and legal liabilities now present as a direct result of their activity in our home. RCW has made no attempt to reconcile the unpaid subcontractors with the over $130K they have collected from us. Although they have collected funds towards these subcontractor unpaid invoices, they have made no effort to make restitution or assure payments. While optimistic they would endeavor to resolve some issues included in the complaint, we have no evidence they have made or will make a genuine attempt to do so. As such, we do not accept their response as a resolution to the complaint.

We have detailed our complaint in the prior iterations, providing dates and specific details to substantiate our claims. Where germane, we have paperwork, photographs, and records verifying our assertions and can provide witnesses who were present for critical actions and discussions. We have limited access to financial files without a subpoena, but a forensic accounting from the materials in our possession supports the financial claims in the original complaint and subsequent rebuttals to RCW. In all areas of our complaint, we have made every attempt to accurately reflect the specifics of what occurred over the last 18 months working with RCW, Bruce R, and Matt R.

We do want to make one correction to our prior complaint. This relates to ***, and his actions once he learned that his builder's license was being used by Bruce R to procure a permit. *** did not ever intend to allow his license to be used by unlicensed contractors. This is a violation of Occupational Code: Act 299, Section 2411 (j). He was concerned when he learned Bruce R attempted to do this, and called the *** Twp. Building Inspector, to make sure this permit was not granted. He did not know his credentials had been used with *** Bank. We were in error in our first rebuttal to indicate a registered letter was sent to the *** Twp. Building Inspector; this was a misunderstanding on our part. The communication between *** and the *** Twp. Building Inspector was by a phone call.

In their response to the initial complaint and subsequent rebuttals, RCW, Bruce Reynolds, and Matt R indicated they knowingly engaged in illegal, unethical, and/or unprofessional activity. We address the most egregious issues below:

1. Working as an unlicensed contractor: RCW admits to knowingly and willingly serving as unlicensed contractors on our project. In their second rebuttal, they state "RCW did express to the *** that we would be a general contractor on their project and did not have a license." This is a violation of Occupational Code: Act 299, Section 2403.
2. Aiding and abetting unlicensed activity: RCW admits to knowingly performing illegal, unlicensed, and unpermitted work. In the first rebuttal they stated, "Reynolds Custom Woodworking did wire a small portion of the renovation on the existing structure without a permit and does no (sic) have a license to do so." The "small proportion" includes: moving and adding lights and outlets throughout the kitchen, living room, halls, new laundry, and new bath; installing wiring for or rewiring a microwave, double oven, cooktop, dishwasher, washer and dryer, and kitchen exhaust hood; running a dryer exhaust vent; installing a gas line; etc. RCW collected funds designated for licensed and skilled plumbers and electricians and knowingly transferred these tasks to their unlicensed employees. Subsequent "Special Inspections" by *** County inspectors indicate significant violations of code for mechanical and electrical work. We have to hire licensed professionals to assure our home and family are safe, we can be properly insured, we can pass a building inspection, and we can close our renovation loan. This is a violation of Occupational Code: Act 299, Section 2411 (j).
3. Failure to obtain appropriate permits: RCW confirmed in their first rebuttal they had stated they would get the required permits, "We did indicate that we would be using permits to do renovations on the home." Later in the same rebuttal they acknowledged they failed to do so, "Reynolds Custom Woodworking did wire a small portion of the renovation on the existing structure without a permit and does no (sic) have a license to do so." The *** Twp. Building Inspector, confirmed the code violation for performing work on our home without appropriate permits (both electrical and mechanical). Alongside paperwork completed by the Building Inspector, we submitted a LARA complaint. Our complaint is under review and is being processed as three separate complaints against Reynolds Custom Woodworking, Bruce R, and Matt R (COMPL-*** - Builders; COMPL-*** - Builders; COMPL-*** - Builders).
4. Failure to have all agreements in writing and signed by all parties: RCW admits to not appropriately documenting added expenses, "There were no signed agreements between Reynolds Custom Woodworking and the client when these changes were made." Despite acknowledging they never followed the appropriate protocol for notifying us of additional costs, RCW continues to insist they are owed substantial amounts of money for items we never approved and bills RCW refuses to share.
5. Failure to ensure written agreements clearly stated terms of transaction: RCW claims we had a fixed-price bid agreement in their second rebuttal. No such agreement or contract was implemented over the 18-month period we worked with RCW. We were never told this was to be a fixed-price agreement and would never have agreed to such given the ambiguity in the estimation process, absence of a written contract, and lack of clarity regarding the project scope. Their claim of a fixed-price bid is inconsistent with the following:
a. An absence of a signed or drafted contract, which we would have required if agreeing to a fixed bid on a $160K project.
b. A lack of documentation supporting this assertion by RCW of a fixed-price bid. (The first documentation of the "bid" assertion was in the second rebuttal to this complaint).
c. The initial transparency, full disclosure of estimates from subcontractors, and conversations regarding costs up through April 2019, when we first noted and documented the occurrence of double billing, billing for items not delivered, and incorrect price modifications.
d. Extensive emails, texts, and detailed conversations we initiated with *** Bank and RCW, during which we operated under the premise and repeatedly and clearly stated we had a cost-plus agreement (materials and labor plus their 5% on materials and 10% on labor).
e. The lack of any attempt on the part of RCW to address, clarify, or rectify this implied fundamental misunderstanding regarding the financial agreement with us.
6. Misrepresentation of Contractor License: The first acknowledgement of the lack of appropriate licensure to serve as contractors was made on the second response from RCW to our complaint. Although they now openly admit they practice as unlicensed contractors, they did not disclose this to us at any time; to *** Bank (for whom they signed documents indicating they would serve as contractors on the project); nor to *** Twp. in June of 2019 when using an inactive license number to apply for a building permit for the addition. As late as December, they were still presenting to us as if they had a contractor's license. Below is an email exchange with RCW on 12/20/19 in response to their registered letter and revised bill (revised bill in RCW rebuttal 2):

Our email: "Before we consider any resolution that involves you doing more work in our home we must see documentation that: 1. You are properly licensed by the State of Michigan to perform the work that needs to be completed. 2. You have all appropriate insurance policies including but not limited to general liability coverage and worker's compensation coverage."

RCW Response: "If you could you (sic) please provide a list of the items that need to be completed at your residence, I would be more than happy to provide you with the information you are requesting."

Check fields!

Write a review of RCW Design

Satisfaction rating
 
 
 
 
 
Upload here Increase visibility and credibility of your review by adding a photo

RCW Design Rating

Overall satisfaction rating

Address: 210 S 1st St, Shepherd, Michigan, United States, 48883

Phone:

Show more...

Web:

This website was reported to be associated with RCW Design.



E-mails:

Sign in to see

Add contact information for RCW Design

Add new contacts
A | B | C | D | E | F | G | H | I | J | K | L | M | N | O | P | Q | R | S | T | U | V | W | X | Y | Z | New | Updated